|
Exploration
and Planning started already in 1947 and was continued for two years in
this 50 km² High Temperature Area, one of at least 27 such resources,
which are directly connected with the most volcanic regions of the
country. A few experimental
boreholes were drilled for the evaluation of the exploitable power and
the chemical composition of the steam.
After
a rather long intermission exploration and research continued with
shorter intervals from 1965 to 1986.
The construction of the Geothermal Power station was commenced in
1987 and continued incessantly until the cornerstone was laid on May the
13th 1990. It was
officially started on September 29th the same year.
The
Hengill Area is amongst the largest High Temperature Areas of the
country. The geothermal activity is closely connected to three active
volcanic systems in the region. The
source of the natural- and
artificial (boreholes) thermal activity in and in the
vicinity of the horticultural village Hveragerdi to the
south of the mountain range is an extinct central volcano,
called 'The Grenjadalur System'. North
of it is still another one, called 'The Hromundartindur System', which
was last active about 10.000 years ago.
The westernmost of the three systems, The Hengill System, has
erupted several times during Holocene and every now and then we are
reminded of the natural forces at large by tremors and earthquakes.
The
Nesjahraun Lava field was created during a fissure eruption of the
Kyrdalur Fissure near the Power station 2000 years ago and at the same
time the largest island of the lake came into being.
Results
of extended research have shown that the precipitation in the mountains
north of the geothermal areas percolates deep down into the earth and
then flows through subterranean faults and fissures to lower regions. On its way the water is heated by the hot rock and resurfaces
as boiling water or steam through fissures extending to the surface or
can be reached by boreholes where there is no obvious thermal activity
on the surface. According
to the scientists, the hot water travels at a depth of only 3 km on the
average, but in places it comes as close as 1 km to the surface.
Because
of extended recent volcanic activity in the area, the rock strata are
relatively young. The
uppermost 500 m consist of
hyaloclastites but beyond that are differently thick layers of basaltic
lavas. Dykes become more
frequent at greater depths and at 1400 - 1600 m they are prevailing.
Water veins are common at the margins of the dykes, especially if
they are acidulous.
The
geothermal gradient of the 'Kyrdalssprunga Volcanic Fissure' is the
greatest in the area. At
sea level the temperature is 100°C and at 2000 m it exceeds 350°C.
Since
1972 the boreholes drilled have been fitted for future exploitation.
The results have been extremely good.
The average hole yields up to 60 mw. of exploitable power on the
average, sufficient for the central heating of a habitation of 7500
people.
All
together 23 holes have been sunk, thereof 13 exploitable.
Four of them were connected at the first stage.
Their total output equals 140 mw.
At the end of the second stage additional 100 mw. will be
exploited, of which 50 were pipelined to the power station in 1991. The remaining 50 MW will be activated this year (1994)
bringing the total output of the station up to at least 200 mw.
The power station is designed for a maximum output of 400 mw. in
the year 2010 and according to estimates the present area can be
exploited economically with an average 300 mw. output for at least 30
years.
Simultaneous
exploitation of the excess steam for electrical production is ideal.
Then the steam is pipelined through turbines.
Some of the holes deliver almost clean steam for that purpose and
are estimated to suffice for up to 80 mw.
The pumps of the geothermal power station use 14 mw. of
electricity at it's maximum output (400 mw.).
A
mixture of water and steam is pipelined from the boreholes to the
station through separators. The
steam continues to the heaters and the turbines.
Exhaust chimneys are used for the excess steam.
In the heaters the steam condenses and the boiling water is
pumped to condense heaters where it heats up cold ground water.
The condense water cools of to about 20°C.
The
separated water from the bore holes containing various minerals, which
are deposited on the inner surface of the heater.
To remove these deposits, steel balls are placed in the current
to pulverize them continuously.
The
cold ground water is supplied through boreholes in the lava field close
to the lake and pumped to containers by the station.
From there it continues to the separator heaters or condense- and
steam heaters, where it is heated to 85°C or 90°C.
The
cold water is saturated with oxygen, which causes corrosion after
heating. To eliminate the oxygen and other gasses the water is boiled
at a lower pressure level. This
process cools the water to 82-85°C.
Eventually a minute quantity of acid steam is added to the water
to eliminate the remnants of oxygen and reduce the ph of the water to
prevent deposits in the pipes. This
tiny quantity of sulphuric acid also prevents oxygen to reaccumulate in
the supply tanks of the capital and lends the funny smell to the water
when we turn on the tabs at home.
The
natural discharge from the Nesjavellir Thermal Area has for centuries
been carried to the lake. The
increased discharge from the power station might affect the organic
life. Therefore constant
research and observations are carried out to spot any changes
immediately. Experiments
with pumping the discharge back into the ground are also continued, as
it has become a known fact, that the circulation of the water can be
overexploited if we are not careful.
The
main buildings of the power station are at an elevation of 177 m above
mean sea level. From there
the hot water is pumped through a pipeline, 90 cm in diameter in the
beginning but narrowing to 80 cm for most of the 27,2 km distance to the
capital. The pumps have
only to be used to conquer the uphill gradient through the mountains to
the 406 m level and after that it free flows downhill to Reykjavik.
The pipeline carries a maximum of1870 l of 100°C hot water per
second. It is thoroughly insulated and the heat loss never exceeds 2°C,
the greater the quantity of water running through, the less the heat
loss. Snow never melts on
the pipeline in winter, which goes to show how well it is insulated.
The
steel pipeline to the surge tank has a diameter of 900 mm and a wall
thickness of 12 mm. It is
designed to carry water up to 96°C hot with a maximum transport
capacity of 1870 litres per second.
From the surge tank the water flows by gravity to storage tanks
on Reynisvatnsheidi and Grafarholt from where it is distributed to
Reykjavik and the nearby communities. Those tanks are at an elevation of 150 m above sea level.
The steel pipeline from the surge tanks has a diameter of 800 mm
and a wall thickness of 8 to 10 mm, depending on the maximum inside
pressure. The steel pipe is
laid mostly above ground and rests on concrete pillars.
It is insulated with rock wool and covered with plastic and aluminum
sheets. Five
kilometres of the pipe is an underground-preinsulated pipeline with
polyurethane insulation and about 17 mm thick polyethylene plastic
cover. From Nesjavellir to
Grafarholt the transmission pipe measures about 27 km in length.
For
design, material, and manufacturing specifications the AD-Merkblātter
and DOM standards were used. Testing
requirements were chosen according to the same Merkblātter, but for
pressure testing of the steam collecting lines the ANSI B 31,1 standard
was used. Due to the mountain slope the elevation difference between
the highest and lowest wellheads is 140 metres.
By using steam for pressure test, this elevation difference had
not to be taken into account, when choosing the pipe wall thickness.
Quality control is based on different control levels, which
includes approval of welders and weld inspectors, and welding
procedures.
All
welders had to have a welding certificate according to DIN 8560, R 2-m
to be accepted at the site. All
welds were marked by initials to keep good record of each welder.
For the steam supply and the piping inside the powerhouse, the
quality standard for the welding and testing were based on the German
AD-Merkblātter HP series. Contractors
were required to keep record of all welds tested and to hand over these
reports to the inspectors at the end of each job.
In the steam supply system welding requirements were according to
the DIN standard 8563, part 3, quality class BS.
The wellheads are prefabricated and welded in a workshop.
Each wellhead is 100% X-rayed and visually inspected on both the
outside and as much as possible on the inside.
The welding method mostly used is manual metal arc welding.
Steam
collecting pipelines have a diameter range from DN 250 to DN 1000.
The pipes are mostly spiral welded and came in random lengths of
about 12 metres. The steel
quality was St-37.0 according to DIN 1626, with certificates according
to DIN 50049, 3.1.B. All
welding seams of the pipes were 100% inspected by ultrasonic testing
during the manufacturing process and the pipes were pressure tested.
All pipes on site were welded with manual metal arc welding
method. 25% of each weld
were ultrasonic inspected. Some
radiographs were taken to compare the result to the ultrasonic
inspection. The pipelines had to be laid through lava fields and down
steep hills with an inclination up to 45°.
Overall welding quality was very high, only small defects were
found, mostly porosity, slag and misalignment in large diameters.
Most of the cold water pipes are ductile iron with sockets, which
do not require welding.
Inside
the powerhouse, most of the pipes are made of stainless steel with a
diameter range from DN 100 to DN 800.
These stainless steel pipes are thin walled and have longitudinal
welds. The manufacturing
process test requirement is similar to the steam collecting pipes.
The most used welding method was TIG welding.
For few weldings, where the back gas shielding was difficult to
achieve, manual metal arc welding was used.
The welding quality control was 25% X-Ray supported by dye
penetrant testing. Only few
minor defects were detected.
The
original transmission pipe design was based on spiral-welded pipes
according to steel quality St 37-3, DIN 17100.
Pipes made from steel quality St 52-3 were offered at the same
price as those made of steel St 37-3.
The St 52-3 pipe material was chosen and due to the stronger
steel, a lower welding factor was required, allowing a reduced welding
control. The total length
(27 km) of the transmission line was divided into three sections.
Erection time was chosen two years to enable Icelandic firms to
carry out the work. Three
Icelandic companies built the pipeline and a forth company made and
erected the concrete fundaments. The
welding method was MMA. The
welds were carried out inside tents, which was obligatory, because of
windy weather and often heavy rain.
Most of the welders preheated the joints to 50-100°C before
welding. The welding rods
were kept in heating boxes on site.
The welding quality required was according to the DIN standard
8563/3, quality class BS. All
welds were inspected visually from the outside and the inside.
Some times the inspectors requested minor repairs, mostly due to
undercuts or incomplete penetration.
After the visual inspection the inspectors chose the welds to be
X-Rayed. Due to the close
visual inspection on the outside and the inside, an X-Ray inspection
amount of only about 2% of the total weld length was required, unless
there was a quality problem with a new welder.
The result from the X-Ray inspection was very good.
Only minor defects were found, like porosity.
Ultrasonic testing was also performed at random places.
The result was also very good.
Each new welder was under strict inspection during the first
weeks. That way the
inspectors noticed very quickly if a welder had problems with fulfilling
the quality requirements. Two
or three welders gave up welding after a short time even though they had
passed the welders test. At
the end of the project a weld report was published.
A part of this project was to dismantle two storage tanks at
Oskjuhlid in Reykjavik and to erect them again at Reynisvatnsheidi.
These storage tanks were built in the year 1968 and all parts
were visually inspected. Some
plates had to be rejected due to deep pitting corrosion and the material
was replaced by a new on. The
inspectors performed the same quality control and inspection as on the
transmission pipe.
This
project is one of the biggest welding and welding quality control
projects in Iceland to this date. The
welding quality control was a part of the task of the construction
supervision team. This
brought the extension of the quality control directly to the Owners
decision. The co-operation
between the welding quality control and the welders was good and no
claims were blamed on the execution of the quality control.
Due to this close co-operation between all involved parties,
quality control was achieved at minimum cost.
The plant and transmission line have been in operation since
1990. No weld failures have
occurred showing so far that the weld quality is satisfying.
|